CMMI – Level 2 – Requirement Management Part1
Process Areas in the Level 2 - Managed
- Requirement Management
- Project Planning
- Project Monitoring and Control
- Supplier Agreement Management
- Measurement and Analysis
- Process and Product Quality Assurance
- Configuration Management
PA Requirement Management
Specific Goal:
SG1 Manage Requirement
Specific Practices:
SP 1.1 Obtain an understanding of Requirements (a stage of static checking before requirement study)
Sub-practices:
- Define the criteria for distinguishing requirement provider.
- Define the criteria for accepting the requirement.
- Analyze requirement to see whether criteria is met.
- Reach an understanding of the requirements.
Typical Work Product:
- Lists of criteria for distinguishing appropriate requirements provider.
- Lists of criteria for accepting the requirements.
- Results of analyses against criteria.
- An agreed-to set of requirements.
SP 1.2 Obtain commitments to the requirements (requirement study stage)
Sub-practices:
- Assess the impact of requirements
- Record the commitments
Typical Work Product:
- Requirements impact assessment
- Requirements / Requirement changes commitment
SP 1.3 Manage Requirement Changes
Sub-practices:
- Record all requirements and requirement changes.
- Record all changes history.
Evaluate the impact of the changes from the standpoint of the relevant stakeholders.(comments: this is mentioned in the official CMMI documents, but actually the practice actually has finished in SP2 seems no need to do it again in the SP 1.3)- Make the requirements and change data available to the project.
- Requirement status
- Requirement database
- Requirement decision database
Typical Work Products
SP 1.4 Maintain Bidirectional Traceability of Requirements
Sub-practice:
- Maintain requirements traceability to ensure that the source of lower lever requirement is documented.
- Maintain requirements traceability from a requirement to its derived requirements as well as to its allocation of functions, objects, people, processes and work product.
- Maintain horizontal traceability from function to function.
Generate the requirements traceability matrix.(comments: duplicated with point 1,2,3)
Typical Work Products
- Requirements traceability matrix
- Requirements tracking system
SP 1.5 Identify Inconsistencies between Project Work and Requirements
Sub-practice:
- Review the project plan, work products for consistency with the requirements and the changes made to them.
- Identify the source of the inconsistency.
- Identify changes need to be done on project plan, work product based on the requirements changes.
- Take the corrective actions.
Typical Work Products
- Documentation of inconsistencies in project plan and work product.
- Documentation of the corrective actions.
The above documents can be included in the system analyze document.